Moving Objects to Zones

This section describes how to move objects to zones on iLOQ Manager.

Note:

If you have created the zone structure as part of the overall system deployment procedure, you do not necessarily have to move objects to zones. However, if you add zones to an existing locking system, you can move existing objects to the zones.

Proceed as follows.

  1. Open the page that contains the objects you want to move to the zone, for example, Basic data > Browse locks.
  2. Select the objects that you want to move.
  3. Right click the objects to select Change zone of a <object>.
    The Change zone of <object> wizard is opened.
  4. Select Change zone.
  5. If necessary, select the objects that will be moved.
  6. Select Next.
  7. Select the zone where the objects will be moved.
  8. Select Next.
  9. A summary screen is shown.
  10. Select Ready.
  11. Select Close.